80 percent physical realization rate achieved in Atatürk Sports Hall construction

Serdar HocamAuthor & Editor

Inspections were carried out on the Atatürk Sports Hall project being built by the Bursa Metropolitan Municipality.

◉ 0 views
Atatürk Spor Salonu'nda sona doğru

Bursa Metropolitan Municipality Deputy Mayor Şahin Biba conducted inspections at the ongoing Atatürk Sports Hall construction site and announced that the project has reached a physical realization level of 80 percent.

Construction Inspections

Bursa Metropolitan Municipality Deputy Mayor Şahin Biba conducted technical inspections at the Atatürk Sports Hall currently under construction and inspected the latest status of the project on-site.

Participants and Delegation

During the technical inspection tour, Deputy Mayor Şahin Biba was accompanied by AK Party Provincial Vice President Cem Kürşad Hasanoğlu, AK Party Osmangazi District President Adnan Kurtuluş, and municipal bureaucrats.

Project Area and Features

Having a total construction area of 18,720 square meters, the facility is being implemented to strengthen Bursa's sports infrastructure.

Increase in Spectator Capacity

The spectator capacity, which was initially planned as 3,000 people at the beginning of the project, was increased to 5,000 people as a result of revision works.

Completed Works

At the current stage of the project, reinforced concrete and steel construction works, as well as roof cladding and necessary retaining structures for landscaping, have been completed.

Ongoing Manufacturing

Terrace insulation, mechanical manufacturing, interior plastering, hardscape applications, and facade works continue to be carried out.